Articles | Volume 6, issue 3
https://doi.org/10.5194/wes-6-949-2021
https://doi.org/10.5194/wes-6-949-2021
Research article
 | 
23 Jun 2021
Research article |  | 23 Jun 2021

Optimal scheduling of the next preventive maintenance activity for a wind farm

Quanjiang Yu, Michael Patriksson, and Serik Sagitov

Download

Interactive discussion

Status: closed
Status: closed
AC: Author comment | RC: Referee comment | SC: Short comment | EC: Editor comment
Printer-friendly Version - Printer-friendly version Supplement - Supplement

Peer-review completion

AR: Author's response | RR: Referee report | ED: Editor decision
AR by Quanjiang Yu on behalf of the Authors (22 Jan 2021)  Author's response   Author's tracked changes   Manuscript 
ED: Publish subject to minor revisions (review by editor) (31 Jan 2021) by Katherine Dykes
AR by Quanjiang Yu on behalf of the Authors (04 Feb 2021)  Author's response   Author's tracked changes   Manuscript 
ED: Publish subject to minor revisions (review by editor) (10 Apr 2021) by Katherine Dykes
AR by Quanjiang Yu on behalf of the Authors (20 Apr 2021)  Author's response   Manuscript 
ED: Publish subject to technical corrections (17 May 2021) by Katherine Dykes
ED: Publish subject to technical corrections (26 May 2021) by Joachim Peinke (Chief editor)
AR by Quanjiang Yu on behalf of the Authors (27 May 2021)  Author's response   Manuscript 
Download
Short summary
There are two ways to maintain a multi-component system: corrective maintenance, when a broken component is replaced with a new one, and preventive maintenance (PM), when some components are replaced in a planned manner before they break down. This article proposes a mathematical model for finding an optimal time to perform the next PM activity and selecting the components which should be replaced. The model is fast to solve, and it can be used as a key module in a maintenance scheduling app.
Altmetrics
Final-revised paper
Preprint